Rita's Process Chart
Rita’s Process Chart outlines the five Process Groups.
The Big Chart
The "Big Chart" is a visual summary of all PMP processes, inputs, tools, and outputs across knowledge areas and process groups.
Inputs, Tools & Techniques, Outputs (ITTOs) Breakdown Tables
The ITTO Breakdown Tables organize and simplify the Inputs, Tools & Techniques, and Outputs for each PMP process to help with memorization and understanding.
Change Management Process Flow
The Change Management Process Flow guides how project changes are requested, reviewed, approved, and implemented.
Risk Management Tools Summary
Risk Management Tools Summary outlines techniques used to identify, analyze, prioritize, and respond to project risks effectively.
Earned Value Management (EVM) Formulas & Interpretation Table
Earned Value Management (EVM) uses formulas to track project cost and schedule performance by comparing planned, actual, and earned work values.
Communication Channels Formula
The Communication Channel Formula calculates the total number of potential communication paths in a project team and is given by the formula: **n(n - 1) / 2**, where **n** is the number of team members.
Agile vs Predictive Project Life Cycles Table
Agile project life cycles focus on iterative, flexible, and incremental delivery with continuous stakeholder collaboration, while predictive (or traditional) life cycles follow a linear, plan-driven approach with defined phases and fixed scope.
Stakeholder Engagement Matrix
The Stakeholder Engagement Matrix maps stakeholders’ current and desired involvement to guide communication and engagement strategies.
Work Performance Data → Information → Reports Flow
Raw data.
Bonus Content
Click here: